Modo Energy · NEM data centre energy policy

How we model data centre contracting

This page sets out the assumptions behind our analysis of what the proposed national data centre energy rules would make NEM data centres contract. We apply the rules as proposed in late 2026 and build the least-cost book of new supply each state's covered data centre load would need in 2035.

Covered loadData centre phases of 30 MW or more that switch on from 2028, at their actual consumption.
RequirementsNew in-state wind and solar for 100% of annual use, and firm cover in every hour.
Least-cost bookThe cheapest mix of wind, solar, batteries and, where allowed, gas engines that meets both.
Contract pricesEach asset priced at what its investors need to build it, and trades its spare output in the market.

Which data centres the rules cover

We assume the national obligations start in 2028. Legislation is due in early 2027, and the Clean Energy Regulator needs about a year to set up the renewable obligation.

Obligations follow consumption

A covered site's obligations track its actual consumption as it ramps up, not its connection capacity. The renewable obligation applies to annual electricity consumption from the time they begin operating, the government says obligations could be linked to this growth, and the firming request lets the AER use the demand ramp profile in each site's connection agreement.

Connection capacity, 100 MWFull load, 43 MW average0 MW50 MW202920302031203220332034203520362037

Example: a hyperscale site with a 100 MW connection that switches on in 2029. Its obligation (bars) follows average consumption on Modo's hyperscale ramp, reaching full load of about 43% of connection capacity after eight years.

Where covered load comes from

Covered load comes from Modo's Central data centre demand forecast, built from a register of project phases. Each phase carries a build probability by status and planning stage, a commissioning delay, a mature draw per MW of IT capacity and a ramp-up curve by operator type. Demand the forecast adds beyond the named pipeline comes from projects not yet identified, so it is covered in full.

We apply the national rules in every state. Queensland data centres buying from state-owned generators could apply to the AER to modify their obligation; we model the national standard as written. Tasmania's proposed campuses exceed 30 MW and carry the same obligations. Our dispatch runs cover the four mainland regions, so Tasmania's covered load takes Victoria's mix per GW, and is left out of cost figures.

What covered data centres must contract

RequirementWhat we modelWhy
EnergyLong-term contracts with new wind and solar in the data centre's state, producing at least 100% of its annual consumption.Energy ministers agreed to mandate that data centres offset their electricity demand by investing in additional renewable generation located in the jurisdiction. The proposed rule only requires certificates, but once all must come from new plant, their price has to cover the gap between a new project's cost and its market earnings. Under the Renewable Energy Target, a similar certificate scheme, new build was mostly financed through PPAs bundling energy and certificates. Contracting the energy also lets that output count towards firm cover in every hour. Annual matching gives data centres flexibility on timing at the lowest compliance cost, and the firm cover test already secures supply in every hour.
Firm coverThe book's own supply covers at least a set share of load in every hour: 70%, 90% or 95%. The article leads with 90%. We stop at 95%, because the last few hours depend almost entirely on how well an operator foresees wind lulls.The firming request asks for cover appropriate to their demand shape and profile and lets the AER assess the full 24-hour profile. AEMO will advise the level. 90% is a strict every-hour test that leaves the market to fill the last tenth in the hardest hours. The request does not set a time step. It would assess contracts, not delivery: the AER would check a portfolio's firmness against the site's demand profile at connection, at reviews every 5–10 years and when load or contracts change. We test hourly because the request asks for supply that meets the timing, duration and magnitude of demand across the full 24-hour load profile, which a daily or monthly energy balance cannot show. Our test checks that the book can physically deliver cover in every hour, a stricter version of the AER's contract test.
LocationAll contracted supply sits in the data centre's state.Ministers made in-state supply the default, unless a state opts out.
Storage minimumBattery power of at least 25% of contracted wind and solar capacity.New South Wales' data centre guidelines set this ratio, the most specific storage rule in the NEM. Batteries sit above this minimum in every state at 90% cover.
Battery ceilingWith gas, contracted batteries are capped at 1.5 GW per GW of data centre load. Without gas there is no cap: batteries are sized for firming only, then scaled up until cover holds.Beyond about 1.5 GW, most of each battery's energy is sold to the market rather than serving the data centre: about 60% at 1.3 GW and up to 73% at 2 GW. More batteries selling surplus would be cheaper than the gas they replace, but the ceiling limits the capital and market exposure a data centre takes on.
Generation capContracted wind and solar output of at most 150% of consumption.Keeps the book to volumes a data centre would sign for, rather than a large overbuild to cover a handful of hours. It does not bind in any state.
Firming technologyFour- and eight-hour batteries in every case; gas, modelled as reciprocating engines, in the with-gas case.The standards allow firming through gas, batteries or hydro. Reciprocating engines run more efficiently than open-cycle turbines at the thousands of hours a year the cover test asks of gas, and come in modules sized for data centre loads. The without-gas case shows the cost if gas is excluded.
Market tradesEvery contracted asset trades in the spot market when the data centre does not need it. Wind and solar sell surplus output, gas engines sell when the price beats their running cost, and batteries charge from the grid and sell back. Market purchases for the load are limited to the share above the cover level.A data centre holding a portfolio of contracts trades its residual position. The firming request does not restrict how storage is charged, and battery contracts such as tolls leave the operator free to trade capacity the data centre is not using.
Battery earnings88% round-trip efficiency and at most one full cycle a day. Each discharge is valued 9–16% below the hourly price, so a standalone battery in our model earns the 2035 energy revenue in Modo's Central forecast for four- and eight-hour batteries in each state. FCAS revenue from the same forecast is added per MW.Our model sees every hourly price in advance. Modo's forecast trades batteries at five-minute resolution with realistic price foresight and is calibrated to the Modo NEM BESS Index, so matching its revenue keeps battery earnings realistic.
Turn-down (tested)The data centre can cut up to 25% of its load for up to 2 hours a day, which counts as cover. Tested, not shown in the charts.The firming request counts dependable demand flexibility, and New South Wales proposes this condition in connection agreements. Two hours a day cannot bridge a multi-day wind lull. Under realistic forecasting it changed gas capacity by between −16% and +1% by state and cost by $0.6–2.6/MWh; without gas it trimmed batteries by 1–4%.

How the firm cover test works

In every hour, wind and solar output, battery discharge and gas must supply at least the cover level. Batteries charge from contracted wind and solar or from the grid, lose 12% of the energy that passes through them, and must be full enough to carry the load through wind lulls. Output the data centre does not need, including from gas and batteries, is sold to the market.

0%50%100%2 April3 April4 AprilDashed line: 90% cover. Grey band above it: market purchases
WindSolarBattery dischargeGas enginesMarket purchases

Illustration: three typical April days for a New South Wales data centre at 90% cover with gas engines, share of hourly load (AEST). Supply is shown renewables first, so wind and solar serve the load before batteries and gas. Operated with realistic forecasts, as described below. Across the year batteries serve about 16% of this site's load and gas about 6%, with gas rising to over half during the longest wind lull.

Checking the book with realistic forecasts

The least-cost model plans the whole year at once, so it knows exactly when every wind lull arrives. A real operator does not. We keep the model's wind and solar and re-run 2035 the way Modo's NEM forecast trades batteries. The book re-plans every hour and acts on the current hour only. It sees that hour exactly. Beyond it, prices are a smoothed six-hour shape, and wind and solar are forecasts that blur towards today's conditions over the next day or two.

The charts show these realistic books. Our wind forecast is off by about 10–11% of capacity a day ahead, similar to a single wind farm's forecast; a diversified portfolio would do better. The check also uses one weather year and sizes top-ups with hindsight, so treat firm capacity as a floor.

New and existing certificates

The renewable obligation lets data centres use some certificates from existing plant at first, rising to all new. We define the new share as the share of a site's annual certificate liability that must come from generation or storage reaching financial close after the obligation starts.

New share in year y = min(100%, (y − 2028) ÷ 6)

Six years follows the Irish glide path the government cites. All certificates are new from 2034, so the wind and solar contracted for 2035 is all new build. Firming comes from new plant in the data centre's region, the firming request's default.

How contracts are priced

Each contract is priced to cover the asset's build and running costs plus investors' required return, set by the cost of capital, over the asset's life. Lenders size debt to the cash flows a long-term offtake provides, so the cost of capital covers both debt and equity.

Contract price ($/kW a year) = installed capex × capital recovery factor (WACC, asset life) + fixed O&M
TechnologyContract price, covered-load average ($/kW a year)Running cost ($/MWh)
Wind291–
Solar133–
Four-hour battery162–
Eight-hour battery259–
Gas engines246125
Open in new tab

What the data centre pays

Average cost ($/MWh consumed) = (contract payments + gas fuel and running costs − net market sales − FCAS income) ÷ consumption

This is the all-in cost of compliance. We show it two ways for the same book. With sell-back, surplus wind and solar, spare battery discharge and spare gas output earn the hourly price, and batteries earn FCAS. Without sell-back, the data centre earns nothing from the market and pays only for its purchases. Both are compared with the average spot price.

Weather, prices and load

Sources