Batteries can submit offers to four of SPP's seven Ancillary Services products

Regulation Operating Reserves Ramp Up Ramp Down Uncertainty
Regulation Up Regulation Down Spinning Reserve Supplemental Reserve
DescriptionCorrect upward frequency deviationsCorrect downward frequency deviationsContingency reserve from online capacityContingency reserve from offline capacityFollow expected upward net-load rampsFollow expected downward net-load rampsCover upward net-load forecast error
Accept offersYesYesYesYesNoNoNo
Response time4 seconds4 seconds10 minutes10 minutes5 minutes5 minutes60 minutes
Duration requirement60 minutes60 minutes60 minutes60 minutes5 minutes5 minutes60 minutes
Requirement400–900 MW400–800 MW500–1,000 MW600–1,000 MW200–1,800 MW200–1,700 MW0–4,100 MW
2025 DA average ($/MWh)$14.49$4.17$6.02$1.00$2.85<$0.01$0.36