ERCOT's Batch Zero timeline: from application to transmission plan

Large-load (75 MW and above) interconnection process. Applicants post $50,000/MW financial security.

11 Jul 2026
Batch Zero process takes effect
24 Jul 2026
Interconnection forms submitted to ERCOT
7 Aug 2026
Projects classified: base, studied, or excluded
Apr 2027
Year 1-6 megawatt allocations issued
Fall 2027
Final statewide transmission plan published